Chickasaw Trail/Lake Underhill Intersection
Project Value: $ 2,397,800
Project Status: Completed - December 2007
Client: Orange County
A/E: CPH Engineers
This project included ½ mile of road widening from two lanes to four lanes including underground utilities, curb and sidewalk, signage and landscaping. A new signalization system from the intersection was also included. The project’s MOT plan was challenging due to the shear volume of traffic.
Collins Rd. Intersection
Project Value: $ 4,185,000
Project Status: Completed – July 2006
Client: City of Jacksonville & JEA
A/E: Ayers Associates
This project included ½ mile of road widening from two lanes to four lanes and re-construction of a major intersection including underground utilities, concrete pavement, curb and sidewalk, drainage structures and pipe, fencing, gravity wall, street lighting, signalization, signage, relocation of overhead transmission lines and a 43,000 cy retention pond.
Sand Lake Rd. & Turkey Lake Rd. Intersection
Project Value: $ 2,339,174.00
Project Status: Completed – April 2009
Client: EDEN SPRINGS DEVELOPER, LLC, fka EB AT COLONY LAKES, LLC
A/E: HDR Engineering
This project included the intersection widening of Sand Lake Rd. & Turkey Lake Rd. in Orlando, Fl. The intersection was widened in all directions to handle the increase in traffic to the surrounding Retail Shopping Centers in the vicinity to this intersection. The project included the widening of a major intersection including underground utility installation/relocation, concrete pavement, curb and sidewalk, concrete retaining wall, drainage structures and pipe, street lighting, signalization, signage and relocating all overhead public utility lines to below ground.
SR A1A & Mickler Rd. Intersection
Project Value: $ 2,185,000.00
Project Status: Completed – March 2009
Client: FDOT District Two
A/E: Comprehensive Engineering Services, Inc. (CES)
Project consisted of ½ mile of road widening from two lanes to three lanes, intersection concrete medians, signalized intersection w/ monotube assembly, three detention ponds, storm drainage system, gravity wall w/ pedestrian pickett railing, sidewalk and signage.